Maputo BRT System

Every day, thousands of commuters make their way from the outer zones of Maputo into the CBD which, until recently, could take up to two hours.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Maputo BRT System

Every day, thousands of commuters make their way from the outer zones of Maputo into the CBD which, until recently, could take up to two hours.

PROJECT INFORMATION

Client:Mozambique Ministry of Transport and Communications
Main contractor:Local South African OEM supported by Atana
Subconsultants:Haskoning (Mozambique), Koleko (SA) and Haskoning (UK)
Date:December, 2025
Location:Maputo, Mozambique
Challenge:Congested, chaotic and unreliable public transport conditions in Maputo, with inadequate infrastructure and no formal BRT system in place
Solution:Feasibility study, system design and tender preparation for a 16.2 km segregated BRT lanes (plus additional mix-traffic lanes) electric BRT corridor with ITS integration, operational planning and community-responsive design
Impact:Halved commute times, secured approximately $200M in grant funding, improved accessibility for nearly one million residents, and laid the groundwork for a high-capacity system serving approximately 400,000 passengers daily

Designing fast, safe, and sustainable mobility in Mozambique

Congestion, unregulated traffic, and informal trade spilling into the streets created chaotic transport conditions that limited access to work, safety, and opportunity.

Many roads and vehicles were in poor condition, and safe, reliable transport remained out of reach for thousands.

Clearing the way

Mozambique’s Ministry of Transport and Logistics (previously the Ministry of Transport and Communications) appointed Atana to lead the planning, design and tender preparation for a world-class Bus Rapid Transit (BRT) system.

The BRT forms part of the Government of Mozambique’s Urban Mobility Project, MOVE Maputo, launched in 2022 through the Ministry of Transport and Logistics, with a dedicated implementation team driving delivery.

The system aims to slash commute times, improve transport safety, promote cleaner mobility, and, in turn, boost the country’s economic productivity.

Atana’s challenge? Conduct a full feasibility study demonstrating the need for the system and its long-term financial and operational sustainability, followed by detailed design and tendering documentation. This study was critical in securing funding to cover all project phases, including the procurement of electric buses.

Putting people first

Atana’s community engagement included a stated-preference survey to understand commuters’ priorities. The top concern? A guaranteed seat on the bus. Commuters reported overcrowding, a lack of dignity, and long, unsafe trips, highlighting the need for a system that values comfort as much as timeliness.

Enhancing local realities

  • Corridor selection: The 22 km BRT route connects high-demand zones, like Zimpeto and Zona Verde, to the Maputo CBD. Corridors were selected based on commuter density, spatial feasibility, and minimal displacement or expropriation in line with World Bank safeguards.
  • Segregated and mixed sections: A 16 km segregated BRT lane connects Baixa da Cidade to Missão Roque, while 13 km of mixed-use lanes extend toward Albazine and Zimpeto.
  • Traffic modelling: Modelled intersections eliminate right-turn crossings, reducing the risk of collisions. Where necessary, U-turn facilities were introduced to maintain traffic flow.
  • Upgrading legacy infrastructure: Navigating outdated, undocumented colonial-era infrastructure, which required additional surveying and stormwater redesign.
  • Smart system integration: The BRT incorporates intelligent transport systems (ITS), including automated fare collection, modern traffic signals, real-time bus tracking and safety mechanisms.
  • Cleaner, cheaper, future-ready: Depot-based overnight charging using Mozambique’s flexible tariff structure, fast-charging stations at the CBD and northern terminal, and lower lifecycle emissions and maintenance compared to diesel buses.
  • Safety in mind: Stations and services were designed to improve safety and accessibility for all users, especially women travelling early in the morning or late at night.

Beyond the brief, Atana successfully:

  • Demonstrated BRT feasibility, unlocking $200M in grant funding from the World Bank;
  • Designed a 16.2 km segregated BRT lanes (plus additional mix-traffic lanes) , electric, ITS-integrated BRT corridor in a constrained urban environment;
  • Reduced commute times from two hours to under an hour for end-to-end trips;
  • Ensured safe and universally accessible stations and operations;
  • Planned 10 modern terminals capable of moving 4,000 passengers per hour per direction, and an estimated 40 million passengers annually;
  • Enabled access for approximately 400,000 daily passengers, with nearly one million residents benefiting from improved roads and accessibility;
  • Proposed inclusive solutions for minibus taxis and informal traders; and
  • Offered operational support, including staffing models, revenue collection, and security protocols.

Collaboration moves things forward

Atana worked closely with Mozambique’s Ministry of Transport and Communications, and the dedicated MOVE Maputo project management unit – both of whom approached the partnership with professionalism, urgency, and gratitude. Their openness and decisive leadership enabled faster decisions and a more robust system design.

Read the full article on this project, here.

PROBLEMS WE’VE SOLVED: Sani Pass Upgrade Sani Pass (P318) is a lifeline for trade and tourism, linking South Africa and Lesotho through one of the region’s most challenging and scenic routes.



As the only road that crosses the summit of the Drakensberg Mountain range, Sani Pass’s steep switchbacks, loose gravel, and sudden weather changes meant local communities faced dangerous journeys to access schools, healthcare, and trade routes.
Find out more 01 / 10 > <
PROBLEMS WE’VE SOLVED: Altis Biologics Bone Processing Facility The future use of the campus had to be re-examined because of the growth in the number of students at Erasmus University Rotterdam (EUR), different ways of working together and the integration of new activities on campus such as startups, culture, sports and living. Find out more 02 / 10 > < PROBLEMS WE’VE SOLVED: Brandwacht Pedestrian Bridge Tucked along the scenic R328 between Mossel Bay and Oudtshoorn, Brandwacht is a small town on one of the Garden Route’s busiest stretches. Find out more 03 / 10 > < PROBLEMS WE’VE SOLVED: Mountain View Project Story
Mountain View is a high-density housing development on the outskirts of Mossel Bay. It offers over 1,000 erven for low-income families in the region. Find out more 04 / 10 > <
PROBLEMS WE’VE SOLVED: Welgedacht Wastewater Care Works Outside Springs, the Blesbokspruit wetland is one of Southern Africa’s largest highveld wetlands. Apart from being internationally recognised, the area also received treated effluent from the Welgedacht Wastewater Care Works. East Rand Water Care Company (ERWAT) commissioned the plant’s Module 2 expansion. Find out more 05 / 10 > < PROBLEMS WE’VE SOLVED: SANAE IV Research Base Project Story
Located 250km inland from the Antarctic ice shelf, SANAE IV has kept South African scientists safe since 1997.

But after nearly two decades of 24/7 operation, its systems were well past their prime. Power systems, water supply, waste management and heating – all critical to survival in Antarctica – were in dire straits.
Find out more 06 / 10 > <
PROBLEMS WE’VE SOLVED: Crystalactor® Water Treatment Mine water typically has a high mineral content, but this was becoming a costly operational headache at one West Rand gold mine.

Calcium and magnesium build-up caused “hard water,” which began to solidify – and clog pipes.
Find out more 07 / 10 > <
PROBLEMS WE’VE SOLVED: Maputo BRT System Congestion, unregulated traffic, and informal trade spilling into the streets created chaotic transport conditions that limited access to work, safety, and opportunity.

Many roads and vehicles were in poor condition, and safe, reliable transport remained out of reach for thousands.
Find out more 08 / 10 > <
PROBLEMS WE’VE SOLVED: George Low-Cost Housing Delivered through the Western Cape Department of Infrastructure and George Municipality, the handovers formed part of a broader effort to accelerate access to adequate housing in the area.

Atana supported both projects through project management and Clerk of Works services spanning planning, design, procurement, contract administration and construction monitoring.
Find out more 09 / 10 > <
PROBLEMS WE’VE SOLVED: Built for continuous progress Toyota’s new parts warehouse is a landmark investment in South Africa’s capability, and a key step in Toyota’s long-term strategy to strengthen local manufacturing and regional exports.

Designed and delivered by Atana as the primary engineering consultant, the project combines sustainability, speed, and technical ingenuity.

Find out more 10 / 10 > <