SANAE IV Research Base Project Story

Located 250km inland from the Antarctic ice shelf, SANAE IV has kept South African scientists safe since 1997.

But after nearly two decades of 24/7 operation, its systems were well past their prime. Power systems, water supply, waste management and heating – all critical to survival in Antarctica – were in dire straits. Without intervention, the base risked system failures that could compromise safety, disrupt research and breach international environmental commitments.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Built for below-zero

SANAE IV Research Base Project Story

Located 250km inland from the Antarctic ice shelf, SANAE IV has kept South African scientists safe since 1997.

But after nearly two decades of 24/7 operation, its systems were well past their prime. Power systems, water supply, waste management and heating – all critical to survival in Antarctica – were in dire straits. Without intervention, the base risked system failures that could compromise safety, disrupt research and breach international environmental commitments.

PROJECT INFORMATION

Client:Department of Public Works
Main contractor:Nolitha (Pty) Ltd
JV partners 
Date: 
Location:Vesleskarvet, Queen Maud Land, Antarctica
Challenge:Critical infrastructure had reached end-of-life, threatening the safety and continuity of South Africa’s Antarctic research programme.
Solution:Atana designed and administered phased upgrades of all core systems with energy-efficient, low-maintenance technologies tailored for Antarctica’s extreme conditions.
Impact:A resilient, sustainable SANAE IV base ready for the next generation of science. Improved system reliability, lower fuel and water use. A safer working environment for researchers and personnel.

Keeping the lights on at -20ºC

In 2015 the Department of Public Works brought Atana on board to refurbish SANAE IV. But with access limited to the Antarctic’s summer months, all work had to be done in a narrow December-February window.

Atana’s challenge? Redesign critical life-sustaining infrastructure in one of the most extreme and isolated environments on Earth without interrupting operations, compromising safety or harming the ecosystem.

Modern systems, minimal footprint

Works spanned Blocks A, B, and C, covering laboratories, medical areas, kitchens, laundries, cold storage, helideck lifting platforms, and structural enhancements like fire escapes, walkways and safety nets.

What Atana upgraded:

  • HVAC system: A full heating, ventilation, and air conditioning (HVAC) upgrade, including advanced heat recovery systems
  • Power generation: Modernised power generation using cleaner, more fuel-efficient engines with heat recovery
  • Snow-to-water solutions: A new high-capacity snow smelter and integrated water filtration and reticulation systems
  • Water-saving drainage: A vacuum drainage system that reduces water use by 70%
  • Effluent treatment: A membrane-based effluent treatment plant with sludge capture and safe disposal protocols
  • Electrical systems: Including new distribution boxes, backup batteries, LED lighting, and copper rails for power efficiency
  • Off-site control technology: A comprehensive Building Management System (BMS) for real-time control and energy monitoring.


How Atana managed under extreme conditions:

  • New systems were pre-assembled and tested in Cape Town before being shipped to Antarctica and transported 250 km inland by Caterpillar train.
  • Refurbishments were modular, low maintenance, and designed for ease of installation and use by a small on-site team.
  • Old systems were only decommissioned once new systems went live.
  • All materials and waste, including sludge and grease, were returned to South Africa for safe disposal, to comply with strict environmental regulations.


Engineering solutions begin with a conversation.

Beyond construction, Atana successfully:

  • Ensured compliance with local and international environmental standards;
  • Tailored systems to accommodate seasonal population shifts;
  • Maintained uninterrupted research and operations;
  • Delivered significant reductions in energy and water use; and
  • Coordinated delivery across four seasons despite weather-related delays.

Twenty more years of discovery

The SANAE IV refurbishment earned the CESA Aon Engineering Excellence Award for Best International Project.

PROBLEMS WE’VE SOLVED: Sani Pass Upgrade Sani Pass (P318) is a lifeline for trade and tourism, linking South Africa and Lesotho through one of the region’s most challenging and scenic routes.



As the only road that crosses the summit of the Drakensberg Mountain range, Sani Pass’s steep switchbacks, loose gravel, and sudden weather changes meant local communities faced dangerous journeys to access schools, healthcare, and trade routes.
Find out more 01 / 10 > <
PROBLEMS WE’VE SOLVED: Altis Biologics Bone Processing Facility The future use of the campus had to be re-examined because of the growth in the number of students at Erasmus University Rotterdam (EUR), different ways of working together and the integration of new activities on campus such as startups, culture, sports and living. Find out more 02 / 10 > < PROBLEMS WE’VE SOLVED: Brandwacht Pedestrian Bridge Tucked along the scenic R328 between Mossel Bay and Oudtshoorn, Brandwacht is a small town on one of the Garden Route’s busiest stretches. Find out more 03 / 10 > < PROBLEMS WE’VE SOLVED: Mountain View Project Story
Mountain View is a high-density housing development on the outskirts of Mossel Bay. It offers over 1,000 erven for low-income families in the region. Find out more 04 / 10 > <
PROBLEMS WE’VE SOLVED: Welgedacht Wastewater Care Works Outside Springs, the Blesbokspruit wetland is one of Southern Africa’s largest highveld wetlands. Apart from being internationally recognised, the area also received treated effluent from the Welgedacht Wastewater Care Works. East Rand Water Care Company (ERWAT) commissioned the plant’s Module 2 expansion. Find out more 05 / 10 > < PROBLEMS WE’VE SOLVED: SANAE IV Research Base Project Story
Located 250km inland from the Antarctic ice shelf, SANAE IV has kept South African scientists safe since 1997.

But after nearly two decades of 24/7 operation, its systems were well past their prime. Power systems, water supply, waste management and heating – all critical to survival in Antarctica – were in dire straits.
Find out more 06 / 10 > <
PROBLEMS WE’VE SOLVED: Crystalactor® Water Treatment Mine water typically has a high mineral content, but this was becoming a costly operational headache at one West Rand gold mine.

Calcium and magnesium build-up caused “hard water,” which began to solidify – and clog pipes.
Find out more 07 / 10 > <
PROBLEMS WE’VE SOLVED: Maputo BRT System Congestion, unregulated traffic, and informal trade spilling into the streets created chaotic transport conditions that limited access to work, safety, and opportunity.

Many roads and vehicles were in poor condition, and safe, reliable transport remained out of reach for thousands.
Find out more 08 / 10 > <
PROBLEMS WE’VE SOLVED: George Low-Cost Housing Delivered through the Western Cape Department of Infrastructure and George Municipality, the handovers formed part of a broader effort to accelerate access to adequate housing in the area.

Atana supported both projects through project management and Clerk of Works services spanning planning, design, procurement, contract administration and construction monitoring.
Find out more 09 / 10 > <
PROBLEMS WE’VE SOLVED: Built for continuous progress Toyota’s new parts warehouse is a landmark investment in South Africa’s capability, and a key step in Toyota’s long-term strategy to strengthen local manufacturing and regional exports.

Designed and delivered by Atana as the primary engineering consultant, the project combines sustainability, speed, and technical ingenuity.

Find out more 10 / 10 > <