Sani Pass
Upgrade

Sani Pass (P318) is a lifeline for trade and tourism, linking South Africa and Lesotho through one of the region’s most challenging and scenic routes.

As the only road that crosses the summit of the Drakensberg Mountain range, Sani Pass’s steep switchbacks, loose gravel, and sudden weather changes meant local communities faced dangerous journeys to access schools, healthcare, and trade routes.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Engineering at 2,874m

Sani Pass
Upgrade

Sani Pass (P318) is a lifeline for trade and tourism, linking South Africa and Lesotho through one of the region’s most challenging and scenic routes.

As the only road that crosses the summit of the Drakensberg Mountain range, Sani Pass’s steep switchbacks, loose gravel, and sudden weather changes meant local communities faced dangerous journeys to access schools, healthcare, and trade routes.

PROJECT INFORMATION

Client:KwaZulu-Natal Department of Transport
Main contractor:Atana
JV partnersSemenya Furumele Consulting, Ndizani Civil Works, Leomat Construction
Date:2020 – 2024
Location:South Africa | Lesotho
Challenge:Sani Pass’s rugged terrain and harsh conditions made travel dangerous, limiting trade, tourism, and community access.
Solution:A high-altitude engineering feat by Atana transformed the 33km gravel pass into a resilient, all-weather road, balancing durability with environmental preservation.
Impact:Safer, year-round access for businesses, tourists, and residents; boosting cross-border trade, regional tourism, and economic growth – while maintaining the pass’s natural beauty.

PROBLEMS WE SOLVED

Taming the mountain

Recognising the need for change, Lesotho and South Africa signed an agreement to upgrade Sani Pass in 2005. The goal? To make Sani Pass safer without losing its rugged beauty or harming its delicate ecosystem.



Atana’s challenge? Transform a treacherous climb via sustainable infrastructure that unlocks new opportunities for trade and safer access for communities, businesses, and tourists.

A smarter, safer pass

  • Reinforced road design: A layered, weather-resistant surface now withstands the extreme freeze-thaw cycle.
  • Advanced drainage system: Smart water management, like Terramesh Gabion retaining walls up to 7m high, prevents erosion and protects local waterways, including the Mkhomazana River.
  • Eco-conscious construction: Concrete faces are lined with form liners to mimic natural rock formations and match the surrounding stone.
  • Logistical ingenuity: Careful planning ensured equipment and materials could be transported along the same terrain being upgraded.
  • Biodiversity preservation: Indigenous plants, trees, and sods were carefully removed before construction and replanted post-build.

Engineering solutions begin with a conversation.

Beyond construction, 
Atana successfully:

  • Empowered local communities through job creation, skills development, and SME involvement; 
  • Restored the historic Good Hope Trading Station as a tourist attraction;
  • Secured Provincial Treasury approvals; and
  • Ensured strict construction and quality standards.

Preserving the past, building a legacy

The Sani Pass upgrade earned the SANRAL SAICE 2022 National Award for Most Outstanding Civil Engineering Project.

PROBLEMS WE’VE SOLVED: Sani Pass Upgrade Sani Pass (P318) is a lifeline for trade and tourism, linking South Africa and Lesotho through one of the region’s most challenging and scenic routes.



As the only road that crosses the summit of the Drakensberg Mountain range, Sani Pass’s steep switchbacks, loose gravel, and sudden weather changes meant local communities faced dangerous journeys to access schools, healthcare, and trade routes.
Find out more 01 / 10 > <
PROBLEMS WE’VE SOLVED: Altis Biologics Bone Processing Facility The future use of the campus had to be re-examined because of the growth in the number of students at Erasmus University Rotterdam (EUR), different ways of working together and the integration of new activities on campus such as startups, culture, sports and living. Find out more 02 / 10 > < PROBLEMS WE’VE SOLVED: Brandwacht Pedestrian Bridge Tucked along the scenic R328 between Mossel Bay and Oudtshoorn, Brandwacht is a small town on one of the Garden Route’s busiest stretches. Find out more 03 / 10 > < PROBLEMS WE’VE SOLVED: Mountain View Project Story
Mountain View is a high-density housing development on the outskirts of Mossel Bay. It offers over 1,000 erven for low-income families in the region. Find out more 04 / 10 > <
PROBLEMS WE’VE SOLVED: Welgedacht Wastewater Care Works Outside Springs, the Blesbokspruit wetland is one of Southern Africa’s largest highveld wetlands. Apart from being internationally recognised, the area also received treated effluent from the Welgedacht Wastewater Care Works. East Rand Water Care Company (ERWAT) commissioned the plant’s Module 2 expansion. Find out more 05 / 10 > < PROBLEMS WE’VE SOLVED: SANAE IV Research Base Project Story
Located 250km inland from the Antarctic ice shelf, SANAE IV has kept South African scientists safe since 1997.

But after nearly two decades of 24/7 operation, its systems were well past their prime. Power systems, water supply, waste management and heating – all critical to survival in Antarctica – were in dire straits.
Find out more 06 / 10 > <
PROBLEMS WE’VE SOLVED: Crystalactor® Water Treatment Mine water typically has a high mineral content, but this was becoming a costly operational headache at one West Rand gold mine.

Calcium and magnesium build-up caused “hard water,” which began to solidify – and clog pipes.
Find out more 07 / 10 > <
PROBLEMS WE’VE SOLVED: Maputo BRT System Congestion, unregulated traffic, and informal trade spilling into the streets created chaotic transport conditions that limited access to work, safety, and opportunity.

Many roads and vehicles were in poor condition, and safe, reliable transport remained out of reach for thousands.
Find out more 08 / 10 > <
PROBLEMS WE’VE SOLVED: George Low-Cost Housing Delivered through the Western Cape Department of Infrastructure and George Municipality, the handovers formed part of a broader effort to accelerate access to adequate housing in the area.

Atana supported both projects through project management and Clerk of Works services spanning planning, design, procurement, contract administration and construction monitoring.
Find out more 09 / 10 > <
PROBLEMS WE’VE SOLVED: Built for continuous progress Toyota’s new parts warehouse is a landmark investment in South Africa’s capability, and a key step in Toyota’s long-term strategy to strengthen local manufacturing and regional exports.

Designed and delivered by Atana as the primary engineering consultant, the project combines sustainability, speed, and technical ingenuity.

Find out more 10 / 10 > <